Home Project-material AN ASSESSMENT OF CONTRACTOR’S RISKS EXPOSURE WITHIN SOME STANDARD FORMS OF BUILDING CONTRACT IN NIGERIA.

AN ASSESSMENT OF CONTRACTOR’S RISKS EXPOSURE WITHIN SOME STANDARD FORMS OF BUILDING CONTRACT IN NIGERIA.

Dept: BUILDING File: Word(doc) Chapters: 1-5 Views:

Abstract

Construction projects are subjected to several risks due to different activities involved. The activities are performed by several parties under different circumstances. Among the various stakeholders the Contractor has been identified to be the party that carries the highest number of risks. They are mostly exposed to contractual risks which occur as a function of contract provisions and clauses. This research work identified and assessed the risks which Contractors are exposed to within some Standard Forms of Contract in Nigeria. It further determined the likelihood of occurrence of the identified risks, impact on the risks on Contractors and the level of risks. Data were collected through questionnaires distributed to some Contractors around Abuja and analysed using qualitative risk analysis technique. The research identified 35 potential risk factors with 54% of the risks emanating from the Clients, 31% from the Architect, 6% from the Quantity Surveyor, 6% from the Proj

CHAPTER ONE

BACKGROUND OF STUDY

The construction industry is a unique and dynamic industry of the economy; in Nigeria it

accounts for over 1.4% of its Gross Domestic Product and also it is a large employer of

labour (Oluwakiyesi, 2011). But over the years it has been criticized for its expensive and

wasteful nature, low productivity, quality problem and project delay. The reasons for all

these being are as varied, diverse and complex as the products of this industry itself. The

process of developing a project from initial investment appraisal to completion and into

use is complex (Flanagan and Norman, 2003). It is a generally recognized fact that those

within the construction industry are continually faced with a variety of situations

involving many unknown, unexpected, frequently undesirable and often unpredictable

factors. These uncertain situations according to Turner (1990) have made many projects to

fall short of the desired objectives of cost, time, quality and satisfaction.

Project Management Institute (2000) defines risk as uncertain event or condition that if it

occurs has a positive or negative effect on the project objective. Bufaied (1987) also

describes risk in relation to construction as a variance in the process of a construction

project whose variation results in uncertainty as to the final cost, duration and quality of

the project. There are many risks involved in construction projects, which could be

attributed to a number of reasons; amongst them are the nature of the construction process,

the complexity and time-consuming design and construction activities, the involvement of

a multitude of people, from different organisations, with different skills and interests, all

resulting in accumulative associated risks for the project. Hence, a great deal of effort is

required to co-ordinate the wide range of activities that are undertaken (Chapman and

Ward, 1997; Shen, 1999). As the size and complexity of the projects have increased, the

ability to manage risks throughout the construction processes has become a central

concern in the attempt to prevent unwanted consequences (Maytoren et al., 2007).

Different project risks have to be allocated to the party to the project on the basis of who

has best qualifications for dealing with a specific risk (Sou, 2000). However, in many

projects there are attempts by parties trying to avoid risks as far as possible and let

somebody else in the value chain deal with the risks. Majority of project risks are usually

borne by contractors (Andi, 2006); this is because contractors are usually visible for

almost the entire project life- cycle, hence contractors are exposed to risks and are

constantly saddled with the responsibility of managing risks and uncertainties inherent in

the project life-cycle.

Studies carried out by Akintoye and Mcleod (1997), Olatunji (2007) Onukwuba et al

(2009) and Tang (2009) identified some risks contractors are commonly exposed to while

executing contracts. These risks are grouped into; Contractual, Political, Performance,

Financial, Technical and Environmental risks. The consequences of these risks factors are

claims, dispute, poor quality work, delay, disruption of work, increase in price of

materials, dispute, and stoppage of work etc. The studies further revealed that contractual

risks have the greatest effect on projects because the actions of parties to contract in

responding to duties and obligations dictate the speed of the project execution and

eventual completion. These challenges prompted this study on risks that contractors are

exposed to within some standard forms of building contracts in Nigeria.

1.2 STATEMENT OF RESEARCH PROBLEM

Akintoye and Macleod (1997) identified contractual risks as a fundamental risk in project

management, recognized as having most adverse consequences on the successful

completion of construction project. Contractual risks was also revealed to be the risk

mostly encountered by contractors in Nigeria (Olatunji, 2007) and identified to have the

consequences of claims, disputes, disruption of work, stoppage of work, lack of coordination,

delays and inflated costs. Since construction projects are often executed under

contractual agreement and impose numerous obligations and duties on parties to the

contract; this study intends to identify common contract provisions that form as risks to

contractors within some standard forms of building contract in Nigeria.

Furthermore, a study carried out in South Africa by Harinarain et al (2008) to identify and

quantify contractors’ risk sources as imposed by Joint Building Contract Committee

(JBCC) Principal Building Agreement Series 2000 found out that the risk sources to the

contractors (ranked from highest to the least) are client, subcontractor, quantity surveyor,

principal agent, architect, engineer, government authorities and suppliers. However,

Chapman & Ward (1997) and Project Management Book of Knowledge (2008) revealed

that it is not just enough to identify risks and their sources without prioritizing them by

assessing and combining their probability of occurrence and consequences, or impact.

Williams (1996) also argue that proper consideration of project risk requires the

consideration of both likelihood and impact of risk. Hence there is a need to carryout

study with reference to the standard forms of building contract that are being used in

Nigeria.

1.3 SIGNIFICANCE OF THE STUDY

Risk has significant impact on construction projects delivery (Ahmad et al., 2007) and the

issue of risk has also become quite topical and its study within the construction industry is

one that needs to be considered in order to have a clearer and structured approach to

handling potential risks. Therefore it has become imperative to critically address risks

exposed to contractors in some standard forms of contract in Nigeria in order to ascertain

not just their sources but also their intensity or severity.

This study would enable contractors pay attention when dealing with stakeholders and

risks associated with them in present and future projects. Furthermore, the study will assist

contractors to be aware of contract provisions that intend to increase their risk and also

expose weak links in the construction process. The research would add and enrich existing

knowledge in the management of risk in the Nigeria’s construction industry.

1.4 AIM AND OBJECTIVES OF THE STUDY

The aim of this research is to assess risks that contractors are exposed to within some

Standard Forms of Building Contract in Nigeria.

To achieve this aim the following are the objectives;

i. To identify potential risk factors contractors are exposed to within the Standard

form of Building Contracts.

ii. To classify sources of these risk factors.

iii. To determine the likelihood of occurrence as well as impact of these risks.


Recent Project Materials

Abstract The broad objective of the study is to determine empirically the impact of power generation capacit...
Word(doc) 1-5 Read More
Abstract The petroleum sector is an indispensable body in Nigeria economy. It has remained the Nigerian big...
Word(doc) 1-5 Read More
Abstract This research work was conducted to investigate the impact of the oil industry on the economic gro...
Word(doc) 1-5 Read More
Abstract The essence of this work has been to determine the effect of non-oil export on economic growth in ...
Word(doc) 1-5 Read More
View More Topics

Browse by Departments